Subcouncil resolution details
Subcouncil 17
Agenda item no
17SUB 6/6/2018
Subject
PROGRESSIVE CAPITAL EXPENDITURE: MAY 2018
Meeting date
Thursday, June 21, 2018
Resolution
Noted
Date closed
Thursday, July 05, 2018
Resolution detail
Ward 48
Cllr Davids was happy to report that most if not all of his projects were completed.
Ward 49
C14.00035-F1 Upgrade of Athlone Stadium – Mr Newman: Priority Assets reported that the contractors were on site and that there was a slight delay as the manufacturing of the tanks took place on site. He said that the project will be completed by the end of June 2018.
CPX.0010154-F1 Landscaping – Bhunga Avenue – Mr Cedras of Recreation and Parks reported an additional R100000 has been secured by the project manager from the line department’s budget for this project. He said that the construction of the embayments was completed. He informed the meeting that the project manager for this project was now a TDA official and he would have to get update reports from that official.
Cllr R Adams also expressed his satisfaction that his projects were completed or almost completed.
Ward 60
Cllr Kleinschmidt stated that he also was satisfied with the expenditure progress of his projects and that the balance of R18 290 was for salaries for the Park Attendants which still needed to be paid.
RESOLVED that:
The content of the Progressive Capital Expenditure: May 2018 be NOTED.
ACTION: Zimlo Lalendle