Resolution detail
Meeting date: 21 June 2018
RESOLVED
Subcouncil supports the recommendation that:
That the motion submitted by Cllr G Peck be supported and recommends that the Sub council approach the Electricity Department to investigate installing highmast lights along the area between Paardevlei, Helderzicht, Victoria Park and Lourentia Park.
Motivation: There is the Eskom servitude and the Melck sloot running through this area. At night dumping of waste takes place, people with bad intentions, selling of drugs and other illegal behaviour use this area regularly. The Victoria Park Neighbourhood Watch requested that the Ward Cllr ask for highmast lights to assist them, when patrolling the area.
MOVER: CLLR G PECK and SECONDED by CLLR V ISAACS with no OBJECTIONS to the motion.
FOR ACTION: CHRYSTAL FRANTZ
Click on the section below to view the resolution details history.
Meeting date: 03/08/2018
Email from Nombini Mafilika of Electricity Dept dated 03/08/2018 refers:
The project has been already scheduled for 2022/23 financial year(see attached email).
But I will squeeze it into 2019/20 financial year.
Meeting date: 28/02/2019
Email from Nombini Mafilika of Electricity Dept. dated 28/02/2019 refers:
The project has been added into 2019/20 financial year.
Meeting date: 13/06/2019
Meeting date: 13 June 2019
Cllr Peck stated that this project has been included in the 19/20 financial year and need to find out the time frames of when the project will be implemented.
RESOLVED
That the Subcouncil follow-up with the Electricity Department as to the timeframes for implementation of the project.
That the item REMAINS on the MRA’s.
Meeting date: 15/08/2019
Meeting date: 15 August 2019
Cllr Peck reported that he seen a letter which is the same dates as what Cllr Isaacs’s project will be implemented and will commence on the 18th May 2020 and end 16th June 2020. He requested that the item be removed from the MRA’s.
RESOLVED
That the item be REMOVED from the MRA’s as the project will be implemented on 18 May and end 16 June 2020 and that follow-up need to be done closer to the time.