Skip to content

Search

Subcouncil resolution details

Subcouncil resolution details

Subcouncil 20

Agenda item no

20SUB 13/9/2023

Subject

PROPOSED PERMANENT FULL AND PARTIAL ROAD CLOSURES REQUIRED TO ACCOMMODATE M3 CAPACITY IMPROVEMENTS BETWEEN HILLWOOD ROAD AND NEWLANDS AVENUE

Meeting date

Wednesday, September 20, 2023

Resolution

Approved

Date closed

Tuesday, October 03, 2023

Resolution detail

RESOLVED that:
 
It be recommended that Subcouncil noted that:
 
  1. Based on the 359 comments received during the public participation on the proposed permanent full and partial road closures, responses to these objections as considered, that the Transport Portfolio Committee recommends to MAYCO and thereafter Council the approval of the following full and partial road closures:
 
  1. Partial closure of Fernwood Avenue at the intersection with the M3 to both
vehicular and pedestrian traffic, Bishopscourt. By means of:
  • Median closure along the M3 at the intersection of Fernwood Avenue, and
  • The conversion of Fernwood Avenue access to a Left-in only, and
  • The removal of the Fernwood Avenue pedestrian crossing.
  1. Partial closure of Upper Torquay Avenue at the intersection with the M3 to
vehicular and pedestrian traffic, Bishopscourt, by means of:
  • Median closure along the M3 at the intersection of Upper Torquay Avenue.
  1. Full road closure of Hillwood Road at the intersection with the M3, to vehicular traffic Bishopscourt, by means of:
  • Median closure along the M3 at the intersection of Hillwood Road, and
  • Full closure of Hillwood Road at the M3, i.e. a cul-de-sac, retaining access to existing driveway.
 
  1. Based on the fact that the full and partial road closures, together with the additional outbound lane between Newlands Ave and Hillwood Road, together with various intersection upgrades, allows for the facilitation of reduced travel time along this major arterial and rationalizes the number of start-stop instances that the Transport Portfolio Committee recommends to MAYCO and thereafter Council the approval of the full and partial road closures as detailed above.

You have disabled JavaScript on your browser.
Please enable it in order to use City online applications.