Subcouncil resolution details
Subcouncil 18
Agenda item no
18SUB 8/10/2020
Subject
PROGRESSIVE CAPITAL EXPENDITURE REPORT : SEPTEMBER 2020
Meeting date
Thursday, October 22, 2020
Resolution
Noted
Date closed
Monday, November 02, 2020
Resolution detail
RESOLVED
-
That Subcouncil 18 NOTES the Progressive Capital Expenditure Report as at September 2020;
-
That Ms J Reisenberg provides the facility details of project CPX.007945-F1: Build Infrastructure Area 4;
-
That Mr A Lindgren submits a progress report with regards to project, CPX.0008859-F3: New Prince George drop-off site.
ACTION: MS J REISENBERG AND MR A LINDGREN