Subcouncil resolution details
Subcouncil 5
Agenda item no
05SUB 21/9/2019
Subject
REVIEW AND RESCIND OF SUBCOUNCIL RESOLUTION NUMBER 05SUB38/08/2019 TAKEN AT THE SUBCOUNCIL MEETING HELD ON 14 AUGUST 2019 WITH REGARD TO THE R4 MILLION MURP PROJECTS
Meeting date
Wednesday, September 18, 2019
Resolution
Approved
Date closed
Thursday, September 26, 2019
Resolution detail
RESOLVED that the Subcouncil SUPPORT the projects as scheduled below for the implementation of the R4 000 000 MURP Operational Funding for the 2019/2020 Financial Year.
ROJECT DESCRIPTION |
BUDGET |
WARD 13: MURP OPERATIONAL PROJECTS |
Maintenance The Hague recreation hall |
150000 |
Maintenance Delft Central sports field |
150000 |
Safety wardens (Public Parks and Facilities ) |
273396 |
Area Cleaning |
212998 |
WARD 20: MURP OPERATIONAL PROJECTS |
Maintenance Delft Swimming Pool |
150000 |
Safety wardens (Pubic Parks and Facilities) |
273396 |
Area Cleaning |
212998 |
WARD 24: MURP OPERATIONAL PROJECTS |
Area Cleaning (Delft Section) |
212998 |
WARD 31: MURP OPERATIONAL PROJECTS |
Artwork – Murals and Mosaics at Entrance to Golden Gate |
150000 |
Beautification of the Entrance to Golden Gate |
150000 |
Area Cleaning in Golden gate |
200000 |
Safety wardens (Pubic Parks and Facilities) |
273396 |
Area Cleaning |
212998 |
WARD 106: MURP OPERATIONAL PROJECTS |
Maintenance Delft South Sports Field |
250000 |
Women for Change Program |
250000 |
Safety wardens (Pubic Parks and Facilities) |
273396 |
Beautification of the Entrance to Ward 106 |
200000 |
Area Cleaning Informal Settlements |
200000 |
SUB COUNCIL 5: ADMINISTRATIVE CAPACITY |
Clerk x 3 Sub Council Office of Sub Council Chairperson |
127 590 |
Subcouncil 5: Community Liaison Officer Project Support |
76834 |
TOTAL PROJECT COST |
4 000 000 |