Subcouncil resolution details

Subcouncil resolution details

Subcouncil 7

Agenda item no

07SUB 19/9/2018

Subject

PROGRESSIVE CAPITAL EXPENDITURE: AUGUST 2018

Meeting date

Monday, September 17, 2018

Resolution

Noted

Date closed

Tuesday, October 23, 2018

Resolution detail

The Project Manager commented as follows: The project is currently out on tender. Closing date for 55Q2018/19 Construction of New Fisantekraal Clinic, closers on 01 October 2018. A contractor is expected to be on site by the end of February 2019. The project has a 15 month construction period and will be completed before the end of the 2019/20 financial year. A revised cash flow will be submitted once the contractor has been appointed.

Click on the section below to view the resolution details history.

Meeting date: 25/04/2019