Work continues to determine the extent of repairs required to a 990mm diameter bulk sewer main that collapsed on Prince George Drive, Retreat, on Sunday, 19 March 2023

​

The Water and Sanitation Directorate has appointed a contractor to determine the extent of the repairs required, and to complete the work.

Over the past week, the contractor has:

  • broken through the road surface and removed the tar
  • excavated a large quantity of sand to get to the affected pipe
  • installed shoring to prevent the excavation site from caving in
  • begun over-pumping the sewage to clear out the collapsed section of the pipe

The final timeframe on the repair work is dependent on the exact extent of pipe replacement required – this will be determined once the pipe (which is between 3,5m and 4m deep) is fully exposed.

The measures currently implemented are there to safeguard the repair crew during the course of their work, as well as the motorists travelling along this route. 

TRAFFIC MANAGEMENT AND ROUTE DIVERSIONS

Since the closure of Prince George Drive, traffic heading northbound has been diverted onto Joe Marks Boulevard, into various side streets (10th, 11th, 12th Avenue and Peter Charles Street), and onto Retreat Main Road to rejoin Prince George Drive in Grassy Park.

This morning, 29 March 2023, Cape Town Traffic Services implemented a contra flow, turning the dual southbound carriageway of Prince George Drive into a two-way from 05:00 until 15:00, on a trial basis, to offer further relief to motorists.

Should the trial be successful, the contra flow will be implemented on weekdays, until the sewer repair has been completed. 

​​

For the afternoon peak, the southbound lane will revert to a dual carriageway heading towards Muizenberg, to accommodate the increase in traffic heading in that direction, and motorists heading northbound will be required to make use of the original diversions via Joe Marks Boulevard.

Residents in the surrounding area who are experiencing sewer overflows as a result of this collapsed bulk sewer are advised to contact the City on 0860 10 30 89 or SMS 31373 or WhatsApp 060 018 1505 or email Water@capetown.gov.za

The City sincerely regrets any inconvenience caused during this time.

 