Road resurfacing project commences in Retreat and Tokai
14 March 2025
Road users can expect some lane closures to accommodate the road resurfacing in the vicinity of Main Road in Retreat and Tokai Road in Tokai‘Road users can expect some lane closures to accommodate the road resurfacing in the vicinity of Main Road in Retreat and Tokai Road in Tokai. Residents and business owners can expect some noise during this time. While we work towards keeping Cape Town moving, we ask motorists to consider using alternative routes where possible during this period and thank you for your patience while works are under way,’ said the City’s Mayoral Committee Member for Urban Mobility, Councillor Rob Quintas.
The following temporary lane closures will be implemented:
- A temporary lane closure along Tokai Road will be in place from Steenberg Road to Main Road during the day and night from 19 March to 2 May 2025.
- A temporary lane closure along Clingendael Close in Tokai will be in place during the day from 19 March to 2 May 2025
- A temporary lane closure will be in place to accommodate night work along Main Road, from Station Road to Zwaan Road in Retreat from 17 March to 20 March 2025
All night work will take place between 19:00 and 04:30.
The works will include:
• Replacing kerbs and channels where the pavement has settled
• Construction of pedestrian shelter islands in the centre of Tokai Road just east of Lismore Avenue
• Removing the existing road surface and resurfacing the pavement
• New road markings will be applied once the project is complete
End
Published by:
City of Cape Town, Media Office