Ongoing routine electricity maintenance for 6 June to 12 June 2022
3 June 2022
The City of Cape Town thanks customers for their patience as we do necessary ongoing routine maintenance on our electrical infrastructure next week in various areas of the metroPLANNED ROUTINE ELECTRICITY MAINTENANCE 6 June to 12 June 2022
| DATE | AREA | LOCATION/STREET | START | COMPLETION FORECAST |
| 6 June | Ottery | Strandfontein, Ottery, Edward and vicinity | 06:00 | 18:00 |
| 6 June | Parow – Churchhill Estate | Church, Frankfort, Scott, 5th and Parow Golf Course | 08:00 | 19:00 |
| 6 June | Durbanville | Diemersdal Farm and Attie van Wyk Primary School | 10:00 | 16:00 |
| 7 June | Newlands | Kildare, Von Holdt, Oak Avenue, Norfolk and vicinity | 06:00 | 18:00 |
| 7 June | Bellville | Irene, De Bron, Heather and Door de Kraal Avenue | 08:00 | 16:00 |
| 7 June | Valhalla Park | Eleanor and Hazel | 08:00 | 16:00 |
| 7 June | Strand | Savanna Mews, Broadway Boulevard and vicinity | 08:30 | 18:00 |
| 7 June | Strand | Green Acres Terrace – Chicago Avenue | 08:30 | 18:00 |
| 7 June | Mfuleni | Nkonjane and Mbindini | 08:30 | 15:30 |
| 7 June | Kirstenhof | Belinda, Cirus, Solinter, Windhover, Lente, Aurora, Aandwind , Ferdinand and vicinity | 08:30 | 16:00 |
| 7 June | Glenhaven | Maximillion, Glenhaven Avenue and vicinity | 09:00 | 16:00 |
| 8 June | Lentegeur | Angelier, Kanferboom and vicinity | 08:30 | 16:00 |
| 8 June | Claremont | Bebington, Oaktree and vicinity | 09:00 | 15:00 |
| 9 June | Somerset West | Mon Blois Lane, Beck and Hazelden Drive | 08:30 | 18:00 |
| 9 June | Tafelsig | Paulsberg, Sugarloaf and Versveld Crescent | 08:30 | 16:00 |
| 9 June | Melkbosstrand | Atlantic Beach Golf Estate and vicinity | 09:00 | 16:00 |
| 9 June | Claremont | St Dennis , St Michaels, Davids, Cook, Mares and vicinity | 09:00 | 16:00 |
| 10 June | Constantia | Constantia Nek Estate | 09:00 | 16:00 |
| 12 June | Fish Hoek | Kommetjie, Hillside, Highway, Ravine Steps, Berg, Main, Second Avenue and vicinity | 06:00 | 18:00 |
| 12 June | Strand | Conradie, Michau, Van Ryneveld, Scarbrow and Gous | 09:00 | 16:00 |
| 12 June | Ottery | Econo-Heat Consumer Complex | 06:00 | 14:00 |
| 12 June | Bellville |
Erf 26351,18 Sacks Circle | 07:30 | 15:30 |
We encourage residents to always double check on the City’s social media channels to see if their area will be affected by the regular electricity maintenance during the week.
Where customers are affected by supply interruptions due to normal maintenance, they should receive a door-to-door notice ahead of the planned work.
*Information is complete and correct at time of publication, but subject to change due to weather and other unforeseen conditions.
*It is standard practice to notify customers of planned maintenance via a pamphlet delivered door-to-door ahead of work.
Please note: The City does not carry out maintenance from Stage 3 and above of load-shedding. Routine maintenance work is cancelled in the event of higher stages of load-shedding being implemented.
Tips:
- Where possible, please switch off appliances at the wall socket ahead of maintenance to reduce the risk of damage caused by power surges.
- The supply could be restored at any time, therefore residents should remember to treat all electrical installations as live for the full duration of the interruption.
City’s service channels (don't log the same request multiple times on multiple channels as this contributes to delays):
Call Centre: 0860 103 089
SMS: 31220 (standard charges apply)
Online: www.capetown.gov.za/servicerequests
End
Published by:
City of Cape Town, Media Office