Ongoing routine electricity maintenance for 16 May to 22 May 2022
13 May 2022
The City of Cape Town thanks customers for their patience as we do necessary ongoing routine maintenance on our electrical infrastructure next week in various areas of the metro.PLANNED ROUTINE ELECTRICITY MAINTENANCE 16 May – 22 May 2022
| DATE | AREA | LOCATION/STREET | START | COMPLETION FORECAST |
| 16 May | Claremont | Imam Haron, Belvedere, Selous, Franklin, Queen Victoria and Chichester | 00:00 | 10:00 |
| 16 May | Hout Bay | Main, Military and Baye Du Bois | 09:00 | 16:00 |
| 17 May | Strand | Da Gama, De Jongh, Fagan, Melkbaai and De Beers | 08:30 | 18:00 |
| 17 May | Strand | Da Gama, Goedehoop, Bosman and Jurgens | 08:30 | 18:00 |
| 17 May | Rocklands | Heinkel, Beechcraft, Junkers, Alouette, Curtiss, Whitley and Avro | 08:30 | 16:00 |
| 17 May | Claremont | Newlands, Mountain, Ellis, Ethel, Eden, Silvia, Bowwood and Josephine | 09:00 | 16:00 |
| 18 May | Strand | Kleinbos, Dickens, Drakenstein and Reitz | 08:30 | 18:00 |
| 18 May | Somerset West | Main, Old Stellenbosch and BP Garage | 08:30 | 18:00 |
| 18 May | Claremont | Basset Road, Lynwood Garden, Treehaven Close and Esher Road | 09:00 | 16:00 |
| 18 May | Plumstead | Portswood, Totnes, Tynemouth, Churchill, Evremonde, Milford, Severn and Tiverton, portion of Basil and portion of Southfield | 09:00 | 15:30 |
| 18 May | The Crest, Durbanville | Joostenberg, Groenberg, Crest View Kanonberg, Limietberg and Goedemoed | 09:00 | 14:00 |
| 19 May | Rondebosch | Rouwkoop, Albion, Oak, Harrow, Riverside, Derry and Edman | 06:00 | 18:00 |
| 19 May | Somerset West | Burchel, Patrys, Reservoir, Kiewiet, Squirrel, Verstel and Camphor | 08:30 | 20:00 |
| 19 May | Durbanville | Kingfisher, Viognier, Silkwood, Lubbe, Fairtrees, Langeberg | 09:00 | 14:00 |
| 22 May | CBD | Concourse substation and vicinity | 06:00 | 19:00 |
| 22 May | Claremont | Roscommon, Dreyer, Main and Stegman | 06:00 | 18:00 |
| 22 May | Durbanville | Erf 15330 Cobble Walk Centre | 06:30 | 11:00 |
| 22 May | Bellville, Erf 34109 | Corner of Durban, Bill Bezuidenhout and Willie van Schoor | 07:00 | 14:00 |
| 22 May | Paarden Eiland | Nereide and Industrie | 08:00 | 16:00 |
We encourage residents to always double check on the City’s social media channels to see if their area will be affected by the regular electricity maintenance during the week.
Where customers are affected by supply interruptions due to normal maintenance, they should receive a door-to-door notice ahead of the planned work.
*Information is complete and correct at time of publication, but subject to change due to weather and other unforeseen conditions.
*It is standard practice to notify customers of planned maintenance via a pamphlet delivered door-to-door ahead of work.
Please note: The City does not carry out maintenance from Stage 3 and above of load-shedding. Routine maintenance work is cancelled in the event of higher stages of load-shedding being implemented.
Tips:
• Where possible, please switch off appliances at the wall socket ahead of maintenance to reduce the risk of damage caused by power surges.
• The supply could be restored at any time, therefore residents should remember to treat all electrical installations as live for the full duration of the interruption.
City’s service channels (don't log the same request multiple times on multiple channels as this contributes to delays):
Call Centre: 0860 103 089
SMS: 31220 (standard charges apply)
Online: www.capetown.gov.za/servicerequests
End
Published by:
City of Cape Town, Media Office