Giving Melkbosstrand’s ageing water pipes a much-needed upgrade
19 November 2026
Water pipe replacements reduce burst risk
More than R6,3 million is being invested to replace 1 120m of 50-year-old water pipes in Melkbosstrand, helping to improve water supply reliability and reduce the risk of future pipe bursts.
Ageing water mains along Bato Way and across Otto du Plessis Drive are being replaced as part of a proactive programme to upgrade Cape Town’s water network and reduce the risk of failures.
Work started in September 2026 and involves replacing the existing 100mm and 150mm pipes with new 110mm and 160mm High-Density Polyethylene (HDPE) pipes. The project is using innovative trenchless pipe-cracking technology, which breaks up the old pipe underground while simultaneously pulling the new pipe into place.
This method offers several advantages over conventional open-trench construction. With fewer excavations required, the work can be completed more quickly, at a lower cost and with less disruption to surrounding roads, properties and residents.

Other advantages include:
- Less damage to surrounding areas: Fewer excavations mean less disturbance to roads, pavements, trees and landscaping, as well as lower reinstatement costs.
- Reduced environmental disturbance: Helps preserve ecosystems, landscapes and trees.
- Less material usage: The procedure frequently uses less material, which promotes sustainability.
- Durable materials: HDPE is a common material used to make replacement pipes since it resists corrosion and lasts longer, meaning fewer replacements are needed over time.
- Widely applicable: HDPE can be used in a variety of soil and environmental conditions, making them versatile for different projects.
- Fewer safety hazards: With fewer open excavations, the risk of accidents and injuries is reduced, enhancing overall project safety.

The existing pipes were installed around 50 years ago and have experienced multiple bursts, making their replacement necessary to improve the long-term reliability of the water network in the area.
While infrastructure upgrades can sometimes be disruptive, using trenchless technology allows this work to proceed with fewer excavations and less inconvenience for the Melkbosstrand community.
The project is scheduled to be completed by December 2026.
Published by:
City of Cape Town, Media Office