M3 roadworks under way with holiday pause planned

The City of Cape Town’s Urban Mobility Directorate has successfully commenced with the roadworks along the M3. Work is being carried out in stages, with shoulder restrictions; pedestrian diversions and temporary lane restrictions applying in different work areas. Residents can be assured that all works will pause over the holiday period. 

This project forms part of the City’s efforts to increase capacity along this busy corridor and includes an additional third outbound lane; widening within the existing median; improvements to the existing road shoulders and targeted intersection upgrades. Traffic signals, road signage, street lighting, and affected services will also be relocated or upgraded where required.
 
What road users can expect
 
Road works over the course of this project programme will continue to take place between 10:00 and 15:00 from Monday to Saturday, weather permitting and provided there are no unforeseen delays.
 
Night work is not being implemented as the required work around existing infrastructure and services requires coordination with various service providers and City departments during the day.
 
The City will confirm the builders’ break dates, when work will resume, and which temporary traffic arrangements will remain in place during the break. Road users are however advised to continue to follow all signage and barriers at the construction areas and should allow additional travel time throughout the implementation of the M3 upgrade.
 
Slower traffic and longer journey times may occur even where lanes remain open, as shoulder restrictions and temporary barriers reduce the space alongside moving traffic.
 
The City acknowledges the inconvenience experienced by motorists and neighbouring residents and thanks them for their patience and cooperation while the team delivers quality road maintenance and upgrades.
 
Upper Sidmouth Avenue to Struben Road

  • The initial phase, including the widening works along the road shoulder and footway of the M3, between Upper Sidmouth Avenue and Struben Road along the M3 outbound is well under way.
  • The estimated completion date of this work is 18 January 2027, if all goes according to plan.
  • No lane closures are anticipated in this work area, although pedestrian diversions and shoulder restrictions may apply.

Newlands Avenue and Rhodes Avenue intersection

  • The Newlands Avenue and Rhodes Avenue intersection upgrade is also currently under way and includes a partial lane drop on the approach to the intersection (approximately 80m from the intersection) which only affects the left turn approach to the intersection while the work is under way. This portion of the project is planned to take place until 19 February 2027, if all goes according to plan.  The works include the intersection widening, service relocations, and upgrades to traffic signals and street lighting.
  • After builder’s break, from 12 January to 19 February 2027, the median island demolition and reconstruction at the intersection will take place. Temporary lane reductions in both directions at the Rhodes Avenue intersection will be in place for this period.
  • The City will ensure that temporary signage, barriers, and traffic controllers are implemented to assist motorists and pedestrians on their commute.

Fernwood Avenue intersection upgrade

The Fernwood Avenue intersection will also undergo an upgrade and so reconstruction and changes to the traffic arrangements have been planned to accommodate these works starting 25 February 2027.
 
A full closure of the intersection for approximately five weeks (if all goes according to plan) will be required followed by a left in only access from the M3. The planned completion date for this intersection is 31 March 2027, if all goes according to plan. The City will however communicate the confirmed dates, extent of the closure, alternative routes, and final access arrangements before implementation.
 
The implementation of these upgrades along the M3 follows a public participation process which was conducted in 2022 and 2023. The City will ensure that the details of each phase of the project is communicated to residents prior to the works and that the public is informed of all developments as the project progresses.