City to rehabilitate portion of stormwater pipeline in Athlone
20 February 2023
The City’s Road Infrastructure Management Department is set to commence with the rehabilitation of the stormwater pipeline along Yusuf Gool Boulevard in Gatesville, Athlone. The work is scheduled to commence this week and is expected to be completed by 23 March 2023, pending unforeseen delays. Read more below:
The work will take place from Monday to Friday between 07:30 and 17:00.
- Cleaning the existing stormwater pipeline including the removal of any tree roots present
- Repairs on the existing stormwater pipe
- Further CCTV inspection in the pipeline to confirm that cleaning, root removal and repairs (if any) have all been completed
- Rehabilitate the existing stormwater pipeline
Published by:
City of Cape Town, Media Office