The Strand Sea Wall construction is progressing well, with the bulk of the work expected to be completed by mid-December. The beach is also expected to be open for public access at the same time.

Residents can look forward to the opening of the first portion of the Strand Sea Wall Phase 2 promenade and beach, with the seawall itself expected to be completed ahead of the builder’s break on 10 December 2026.

The remaining construction works will then resume on 11 January and is planned to be completed in February 2027.

Residents are to please take note of the following ahead of the December and January break:

Promenade and beach access

  • The promenade and beach (Mosterd’s Bay beach) between the Strand Municipal Swimming Pool and Haarlem Road will be open to the public.
  • The promenade and beach between Adshade Road and Jackson Black will also be open to the public, although the adjacent promenade will be completed in the new year.
  • Beach access will be available via the newly constructed beach access points from the promenade.
  • The promenade between Haarlem Street and Greenways Estate will remain closed for final works to be completed after the builder’s break.

Traffic arrangements:

  • Beach Road and the associated on-street parking between Strand Municipal swimming pool to Haarlem Road will be complete and open to two-way traffic.
  • Beach Road between Haarlem Street to Greenways Estate will remain a one-way system for northbound traffic (toward Cape Town).
  • Southbound traffic (towards Gordons Bay) will be diverted from Beach Road onto Haarlem Street, and continue via Haarlem Street rejoining Beach Road at the intersection at Greenways Estate
  • Access to all beachfront properties, businesses and driveways will be maintained in the one-way section.

Parking:

  • A temporary public parking area will be made available in the one-way section as on-street parking in this area will remain closed.
  • The parking area at Haarlem Street will be partly accessible to the public.
  • The parking area next to the Strand Municipal swimming pool will remain secured for construction storage, while providing beach and emergency access and access for sewer infrastructure maintenance teams.

The contractor will secure and monitor the site, maintain safe public access, and ensure that unfinished areas are properly isolated during this time.