Click on the section below to view the resolution details history.
Meeting date: 20/03/2024
20 March 2024:RESOLVED unanimously by Subcouncil 2
That the contents of the report, Progress Report on the Re-Construction of the Bloekombos Community Hall BE NOTED;
That an investigation on (a) above be requested as to why the previous contractor could not continue with the work as the project experienced tremendous cost and time delay.
ACTION: RIAAN ISMAIL / AMELIA VAN RHYN
Meeting date: 17/04/2024
17 April 2024:
RESOLVED unanimously by Subcouncil 2
a) That the contents of the report, Progress Report on the Re-Construction of the Bloekombos Community Hall BE NOTED;
b) That an investigation on (a) above be requested as to why the previous contractor could not continue with the work as the project
experienced tremendous cost and time delay.
ACTION: RIAAN ISMAIL / AMELIA VAN RHYN
Meeting date: 17/07/2024
17 July 2024:
RESOLVED unanimously by Subcouncil 2
a) That the contents of the feedback on the Re-Construction of the Bloekombos Community Hall BE NOTED;
b) That an investigation on (a) above be requested as to why the previous contractor could not continue with the work as the project
experienced tremendous cost and time delay;
c) That the ward councillor, Cllr S Duka be provided with a ward office.
ACTION: ALD MARIAN NIEUWOUDT / GIRSHWIN FOULDIEN /LEEROY MAY
Meeting date: 21/08/2024
21 August 2024
RESOLVED unanimously by Subcouncil 2
a) That the contents of the feedback on the Re- Construction of the Bloekombos Community Hall BE NOTED;
b) That additional information be obtain from the department in (a) above in terms of the budget constraints, why the hall was built on a water servitude and who approved the building plan etc?
ACTION: GIRSHWIN FOULDIEN / SECRETARIAT
Meeting date: 18/09/2024
18 September 2024:
RESOLVED unanimously by Subcouncil 2
a) That the contents of the feedback on the Re-Construction of the Bloekombos Community Hall BE NOTED;
b) That a feedback report be obtain from the department in (a) above in terms of the1. Feedback on why there was a budget constraints;
2. Why the hall was built on a water servitude and if this was rectified and if the previous hall was built on the same origin; 3. Who approved the building plan? 4. Confirmation if the contractor is on site to complete the work.
ACTION: REDWAAN HASIEM / ZAHRA NOORBUCKUS
FOR INFORMATION: GIRSHWIN FOULDIEN / SECRETARIAT