Agenda item no

16SUB 7/3/2023

Subject

PROGRESSIVE CAPITAL EXPENDITURE: FEBRUARY 2023

Meeting date

Monday, March 13, 2023

Resolution

Noted

Date closed

Friday, March 31, 2023

Resolution detail

RESOLVED that:

  1.  the Progressive Capital Expenditure: February 2023 BE NOTED.
  2.  Recreation and Parks Project Managers be invited to the Subcouncil 16 Acivity Day.   
  3. Electricity Department officials to respond to the following questions pertaining to Electricity projects for Area North as per the Progressive Capital Expenditure Report;
 
  1. Mr Craig Daniels / Ms Fazila Moosa:
  1. Which substations in Subcouncil 16 was upgraded?
  2. What was spend in Subcouncil 16 and on which projects?
  3. Provide maps depicting which areas in Green Point Precinct are
     excluded and included from load shedding during event days?
    
  1. Ms Maurisha Hammer:Project CPX.0011115-F4 Electrification Area North
FY 23
  1. What was spend in Subcouncil 16 area and on which projects?
  2. Projects for Subcouncil 16 area for the new financial year?
 