Subcouncil resolution details
Subcouncil 16
Agenda item no
16SUB 7/3/2023
Subject
PROGRESSIVE CAPITAL EXPENDITURE: FEBRUARY 2023
Meeting date
Monday, March 13, 2023
Resolution
Noted
Date closed
Friday, March 31, 2023
Resolution detail
RESOLVED that:
-
the Progressive Capital Expenditure: February 2023 BE NOTED.
-
Recreation and Parks Project Managers be invited to the Subcouncil 16 Acivity Day.
-
Electricity Department officials to respond to the following questions pertaining to Electricity projects for Area North as per the Progressive Capital Expenditure Report;
-
Mr Craig Daniels / Ms Fazila Moosa:
-
Which substations in Subcouncil 16 was upgraded?
-
What was spend in Subcouncil 16 and on which projects?
-
Provide maps depicting which areas in Green Point Precinct are
excluded and included from load shedding during event days?
-
Ms Maurisha Hammer:Project CPX.0011115-F4 Electrification Area North
FY 23
-
What was spend in Subcouncil 16 area and on which projects?
-
Projects for Subcouncil 16 area for the new financial year?