Meeting date: 07/03/2019
SUBCOUNCIL : Ward Allocation Projects 2018/19: 28 February 2019
Reference Project Name Budget Expenditure % Complete Comments
CPX.0013722-F1 Pedestrian facilities - Strand CBD 80.000 0,00 99.88% Completed
CPX.0013748-F1 Traffic Calming - Ward 83 60.000 40 000,00 66.67% Balance of funding (R 20 000) to be spent on identified traffic calming
CPX.0013759-F1 Sidewalk Construction - Ward 83 130.000 129 987,00 99.99% Completed
CPX.0013809-F1 LPR Cameras - Ward 83 240.000 0,00 0% Project in progress. Contractor busy with costing.
CPX.0013903-F1 Upgrade Lourens River and Dick Dent 100.000 10 799,25 10.80% Bins have been installed. Pathway installation will begin end March 2019, after ground leveling has been completed.
WPX.0000430 Area Cleaning - Asanda Village 60.000 33 512,02 55.85% Project is in progress, challenges experienced with EPWPs that do not return for cleaning jobs, randomisation targets are not met - address problem
WPX.0010731 Cleaning Lourens River 40.000 0,00 0.00% Project planning took place with Ward Councillor
WPX.0010828 Small business development - Ward 83 40.000 0,00 0.00% Procurement of service provider in progress
WPX.0010834 Grants-in-Aid - Ward 83 50.000 0,00 0.00% Was approved by GIA Committee referred to Council for final recommendation at the March 2019 Council meeting
WPX.0010971 Employ Outreach Workers - Ward 83 40.000 4 863,36 12.16% Project is in process of being implemented
WPX.0011024 Youth Skills Development - Ward 83 30.000 1 027,21 99.77% Completed
CPX.0013733-F1 Purchase of Loudhailers - Ward 85 10.000 8 069,83 80.70% Completed - savings realised
CPX.0013750-F1 Traffic Calming - Ward 85 20.000 20 000,00 100.00% Completed
CPX.0013761-F1 Sidewalk Construction - Ward 85 140.000 139 992,00 99.99% Completed
CPX.0013984-F1 Upgrade Parks - Ward 85 50.000 48 067,09 96.13% Completed
WPX.0000420 Area Cleaning - Ward 85 100.000 43 744,74 43.74% Project is in progress, challenges experienced with EPWPs that do not return for cleaning jobs, randomisation targets are not met
WPX.0010710 Canal Cleaning - Ward 85 90.000 0,00 0.00% Project planning took place with ward councillor
WPX.0010744 Capacity Building Event - Ward 85 40.000 0,00 0.00% Event will take place on 16 March 2019
WPX.0010784 Capacity Building Dialogue - Ward 85 50.000 0,00 0.00% Event will take place in March 2019
WPX.0010836 Grants-in-Aid - Ward 85 50.000 0,00 0.00% Was approved by GIA Committee referred to Council for final recommendation at the March 2019 Council meeting
WPX.0010902 Sports Festival - Ward 85 50.000 9 639,31 79.44% Meeting to be arranged with Ward Councillor to complete the implementation of the project within the 2019 school holidays
WPX.0010981 Heritage Day Event - Ward 85 50.000 46 200,00 98.51% Completed
WPX.0011005 Youth Day Event - Ward 85 50.000 0,00 0.00% Project planning taking place for implementation on 16 June 2019
WPX.0011025 Youth Skills Development - Ward 85 100.000 0,00 98.45% Completed
WPX.0011080 NW Support Programme - Ward 85 50.000 26 079,90 66.81% Partial orders was delivered already, waiting on additional orders, Body/Action Camera’s, Rechargeable Batteries and Chargers. The suppliers are expected to deliver from the 11/02/2019 onwards, as soon as they do we will deliver to your offices
CPX.0013751-F1 Traffic Calming - Ward 86 100.000 99 998,00 100.00% Completed
CPX.0013762-F1 Sidewalk Construction - Ward 86 100.000 99 999,60 100.00% Completed
CPX.0013819-F1 Abattoir Sportsfield - Upgrade 100.000 99 733,40 99.73% Completed
CPX.0014913-F1 Purchase of Loudhailer - Ward 86 10.022 0,00 99.78% Completed
CPX.0015192-F1 Development of Parks - Ward 86 200.000 0,00 0.00% Project planning finalised
WPX.0009417 Area Cleaning - Ward 86 100.000 35 854,30 35.85% Project is in progress, challenges experienced with EPWPs that do not return for cleaning jobs, randomisation targets are not met
WPX.0010745 Capacity Building Event - Ward 86 40.000 0,00 100.00% Event took place on 2 March 2019
WPX.0010811 Sports Tournament - Ward 86 60.000 2 860,05 17.55% Project planned to take place in March 2019
WPX.0010837 Grants-in-Aid - Ward 86 100.000 0,00 0.00% Was approved by GIA Committee referred to Council for final recommendation at the March 2019 Council meeting
WPX.0011026 Youth Skills Development - Ward 86 50.000 0,00 0.00% Project in progress
CPX.0013847-F1 Outdoor Gym Equipment - Casablanca 200.000 157 779,43 78.89% Project in progress
CPX.0013892-F1 Gordon's Bay beach - Paving upgrade 200.000 56 066,40 89.13% Capital comments wiil be loaded from SAP.
WPX.0009286 Part Time Traffic Attendant - Ward 100 40.000 16 666,65 41.67% Project in planning
WPX.0009370 Area Cleaning - Ward 100 300.000 81 341,32 27.11% Project is in progress, challenges experienced with EPWPs that do not return for cleaning jobs, randomisation targets are not met
WPX.0010950 Employ Outreach Workers - Ward 100 60.000 10 030,68 16.72% Project in progress
WPX.0011021 Youth Skills Development - Ward 100 50.000 0,00 0.00% Project in progress