|
A second attempt by the Cape Town
Environmental Protection Association (CEPA) to stop work at the
construction site of the new Green Point stadium failed
today.
An application by the CEPA for an interdict to stop
the demolition of the existing Green Point stadium today was not
pursued. CEPA’s legal team conceded that the demolition, such
as was planned, had been completed and that an interdict to stop it
could therefore not be granted.
The City’s and FIFA 2010
World Cup Organising Committee’s legal teams argued that CEPA should
pay the costs of the two interdict applications. Judgement was
reserved.
In the meantime, construction on the new stadium is
progressing according to programme in order to meet the FIFA
deadline for its completion by the end of October 2009.
The
City of Cape Town has opposed all three legal challenges by
CEPA. The first is an application to review approvals given by
the Provincial Government and the City of Cape Town for the
construction of the new stadium. This is still pending as has
not been heard. On Friday CEPA sought an interdict to stop the
demolition. The application was not heard and the interdict
not granted.
Their third application – again to obtain
an interdict to stop the demolition – failed today. The
City of Cape Town is one of seven respondents. FIFA and its local
Organising Committee have also been cited.
A portion of the
grandstand of the existing stadium has been retained. The site, once
cleared, will be used as a construction yard for the new 68 000
seater multi-purpose stadium.
The demolition of the stadium
is not legally linked to the construction of the new stadium.
The City Council gave two separate approvals and these approvals
have not been challenged.
Enquiries: Pieter
Cronjé, 082 465 4965
|